Data Center Large Load Tariffs 2026: Utilities Now Bill AI Campuses for Power They Never Use
Ten large load tariffs compared. Where a minimum bill is set, AI campuses pay for 75% to 85% of the power they reserve, sign for 15 years and post collateral. Factories over 50 MW can land in the same class.

On November 16, North Carolina regulators approved new Duke Energy rates that include a separate rate schedule for data centers above 50 MW. Duke says it has already signed service contracts for 6.7 gigawatts of large customer load in the Carolinas, 92% of it data centers. That is roughly 6.2 GW of data center demand under contract at one utility.
North Carolina is not alone. In the first three weeks of November, Florida regulators rejected Duke’s large load tariff, Oklahoma created a new rate class for loads over 75 MW, and Kentucky Power filed plans for a new gas plant built around one 1 GW data center campus. The pattern across these decisions is clear enough to state as a claim.
The claim
The era of the open grid for AI campuses is over. Utilities and regulators are converging on one model: if you reserve a large block of power, you pay for most of it whether you use it or not, you sign for 10 to 20 years, and you post money up front. Where the rules state a minimum bill, the floor runs from 75% to 85% of reserved demand. The big cloud companies can absorb that. Smaller developers, speculative campuses and any factory big enough to land in the same rate class will feel it more.
The evidence
The count of these tariffs has jumped. The Smart Electric Power Alliance counted 29 large load tariffs approved in 2025, against 14 in all of 2018 to 2024. A tracker run by the NC Clean Energy Technology Center and SEPA listed 77 approved and proposed tariffs at 60 utilities in 36 states as of March 31, 2026, 51 of them approved.
We pulled the terms of ten recent decisions and filings into one table. Blank cells mean the source we read did not state the term, not that the term does not exist.
Large load tariffs compared
| Utility (state) | Status and date | Size trigger | Minimum bill | Contract term | Exit or security terms |
|---|---|---|---|---|---|
| Duke Energy Carolinas and Progress (NC) | Approved Nov 16, 2026 | Data centers over 50 MW | 75% of contracted demand (as proposed) | 10 or 15 years by size (as proposed) | Stranded Generation Charge; security up front; early exit 25% of remaining bills (as proposed) |
| Dominion Energy (VA) | In effect | Not stated in source | 85% of transmission and distribution demand | 14 years | Collateral required |
| Consumers Energy (MI) | Approved Nov 6, 2025 | 100 MW, or 100 MW aggregate with 20 MW sites | 80% of contract capacity | 15 years plus up to 5 year ramp | Exit fee equals minimum bill times months left; collateral half of exit fee |
| Pennsylvania PUC model tariff | Final order Apr 30, 2026 (nonbinding) | 50 MW, or 100 MW aggregate | 80% minimum demand charge | 5 years after ramp | Graduated collateral; 48 month notice for exit |
| Xcel Energy (MN) | Approved May 15, 2026 | Not stated in source | Not stated in source | 15 years minimum | Early exit fee of 80% of demand charges |
| We Energies (WI) | Decision Apr 24, 2026 | 100 MW (cut from 500 MW proposed) | Not stated in source | 15 years minimum | Pays 100% of generation cost (75% option removed) |
| Portland General Electric (OR) | Approved Jul 7, 2026 | 20 MW | Not stated in source | 10 to 30 years by size | Charges if built capacity goes unused; data center rate up 29.7% |
| Public Service Co. of Oklahoma (OK) | Interim order Nov 5, 2026 | Over 75 MW | Deferred | Deferred | Supply option (own generation, utility, or mix) sent for more study |
| Duke Energy Florida (FL) | Denied Nov 3, 2026 | 50 MW | None proposed; existing rates | 20 years (proposed) | Advance payment for line extension (proposed) |
| Kentucky Power with TeraWulf (KY) | Filed Nov 13, 2026 | Up to 1 GW by 2029 | Not stated in release | Not stated in release | Financial backing required; TeraWulf pays plant financing costs and $100M in bill credits |
Sources for each row are listed at the end. Duke North Carolina’s 75%, 10 or 15 year and 25% exit terms are from Duke’s proposal as reported by Latitude Media; the approved order’s final numbers were not in the coverage we could read. The Dominion terms are also as Latitude Media summarized them.
What the table says
Four of the ten set out a minimum bill: 75%, 80%, 80% and 85%. The simple average is 80%. Pennsylvania’s commission put the logic in one line, saying an 80% minimum demand charge “reasonably incentivizes accurate load projection.” In plain terms: if you ask for 100 MW, you pay for at least 80 MW every month, so you stop asking for 100 MW when you need 40.
Contract terms cluster at 15 years. Consumers, Xcel and We Energies all set 15 year minimums. Duke Florida asked for 20. Portland General Electric scales from 10 to 30 years by project size. Pennsylvania is the outlier at 5 years, but its clock starts only after the load ramp ends.
Exit costs are where the real money sits. Under the Michigan rules, a customer that leaves early pays the minimum monthly bill multiplied by the months left on the contract, and must post half of that exit fee as a letter of credit or cash. Parent company guarantees are not accepted. Xcel’s version charges 80% of demand charges if a facility exits early.
The size trigger is falling. Wisconsin regulators cut We Energies’ threshold from 500 MW to 100 MW and removed an option that let data centers pay for only 75% of generating costs. Portland General Electric’s trigger is 20 MW. Pennsylvania lets utilities apply its model below 50 MW at their discretion.
Who pays when the rules bite
The North Carolina order shows how the money moves. Duke’s own release lists upfront dedicated facility payments, transmission upgrade financial requirements and security requirements for data centers. Residential customers still see increases: at 1,000 kWh a month, a Duke Energy Carolinas bill rises $6.53 on January 1, 2027 and another $4.66 a year later, $11.19 in total. A Duke Energy Progress bill rises $9.62 and then $5.89, $15.51 in total.
Oregon went further. Portland General Electric’s new data center rate settled at a 29.7% increase for the reclassified data centers, while residential rates fell 1.3% and industrial rates fell an average 1.4%.
Florida shows the other side. The commission denied Duke’s tariff on November 3 because Duke did not show its proposed rates and protections would recover each large customer’s full cost of service. Duke had proposed 20 year terms and advance payments, but service under existing rate schedules. A long contract was not enough without a rate that covered the cost.
Kentucky shows the bespoke route. Kentucky Power’s November 13 filing pairs a new 760 MW combined cycle gas plant at Big Sandy with TeraWulf’s Muskie campus, which could reach 1 GW of contracted demand in phases by 2029. TeraWulf agreed to pay the plant’s estimated financing costs, fund $100 million in winter bill credits for residential customers over the first 10 years, and the utility cites more than $500 million in fixed cost offsets over the contract’s life. Decisions could come as early as mid 2027.
What it means on the ground
First, power is now a fixed cost, not a variable one. A data center developer used to model electricity as price times usage. Under an 80% floor, a 100 MW reservation carries the bill for 80 MW from the day the ramp ends. If chips arrive late, if a tenant walks, or if the model training contract shrinks, that bill keeps coming. Lenders will price that, and it favors developers with signed, creditworthy tenants over speculative builders.
Second, collateral eats capital before a single rack goes in. Michigan’s rule of half the exit fee in cash or a letter of credit, with no parent guarantee, ties up real money on day one. Pennsylvania’s graduated collateral is refunded as ramp milestones are met. Either way, the balance sheet decides who builds.
Third, factories can land in the same rate class. Pennsylvania’s model covers any customer over 50 MW. Oklahoma’s new class is any load over 75 MW. Michigan’s tariff amends a general primary demand schedule. A chip fab, a battery cell plant, an electric arc furnace or a large aluminum smelter can cross those lines. North Carolina wrote its schedule for data centers, but not every state is drawing that distinction. A manufacturer planning a big expansion should read its utility’s large load filing before it signs a site.
Fourth, the long contracts change the gear buyers’ calendar. Utilities that can point to 15 year take or pay contracts can finance new plants and substations with more confidence. That firms up demand for turbines, transformers and switchgear that are already backlogged, as our gas turbine analysis showed. It also means the queue is now made of committed load, not wish lists, which should make the backlog numbers on utility calls more real.
Brandon’s Take
From the tooling side, this looks familiar. In custom molding, nobody cuts steel for a large program on a promise. The buyer pays for the tool, commits to volumes, and if they walk, the shop is made whole for the capacity it built. Utilities are now writing that same deal into tariffs, just with substations and gas turbines instead of molds. An 80% minimum bill is a capacity reservation with teeth.
The part I would watch hardest is the size trigger. Most of these rules were written with hyperscale campuses in mind, but the language often says “large load,” not “data center.” A 60 MW battery plant or fab expansion can end up with the same 15 year commitment and the same collateral as an AI campus. Reshoring plans that assumed cheap, flexible industrial power need a second look. The good news is that clear rules beat the old system of first come, first served queues full of phantom projects. Committed load means the wires and plants actually get built.
What to watch
- The North Carolina order text. The final minimum bill percentage, contract terms and exit fee in the approved Duke schedule. New rates start January 1, 2027.
- Duke Florida’s refile. Florida staff recommended Duke be allowed to refile within 10 business days of the written order. The docket’s eight month date is December 22.
- Oklahoma’s supply question. PSO’s large load class still lacks an answer on who builds the generation. OG&E’s large load tariff goes before the commission January 12.
- PacifiCorp in Oregon. A decision on Pacific Power’s large load rate was expected this month.
- Wyoming. Rocky Mountain Power’s Schedule 400 for loads over 200 MW is in a pending rate case, and the state counts over 5 GW of planned hyperscale capacity.
- Kentucky’s ruling. Whether regulators accept a utility building a 760 MW plant for one customer, with that customer paying the financing.
Related: what AI data centers now pay per kilowatt of gas power and how voters drew a 25 MW line through the AI buildout.
Sources
- WFAE, Nov 17, 2026: Duke Energy rates are going up next year
- Duke Energy release via PR Newswire, Nov 17, 2026
- Latitude Media, Jul 8, 2026: Duke’s proposed large load terms and Dominion comparison
- WUNC, Oct 7, 2026: Duke large load settlement
- Environment and Energy Leader, Nov 6, 2026: Florida rejects Duke’s large load tariff
- GCN, Nov 16, 2026: Oklahoma approves PSO rate change and data center tariff
- GCN, Aug 28, 2026: Oregon approves PGE large load rate
- Fresh Energy, May 15, 2026: Minnesota PUC approves Xcel tariff
- National Law Review (Varnum), Nov 7, 2025: Michigan PSC approves Consumers Energy tariff
- Pennsylvania PUC release, May 13, 2026 and final order, docket M-2025-3054271
- Public Service Commission of Wisconsin, Apr 24, 2026: We Energies tariffs
- Kentucky Power release via PR Newswire, Nov 13, 2026
- Utility Dive, May 18, 2026: SEPA tariff counts
- NC Clean Energy Technology Center, Apr 20, 2026: tariff tracker
- FactSet Insight, Oct 14, 2026: Wyoming rate cases
This is analysis, not investment advice.