Data Center Ballot Measures 2026: Voters Drew a 25 MW Line Through the AI Buildout

Voters went against data centers in 40 of 41 local ballot measures on November 3. The number that matters is 25 MW: six towns now cap data centers there, which rules out every AI campus now being planned.

Data Center Ballot Measures 2026: Voters Drew a 25 MW Line Through the AI Buildout
Image: Tedder, CC BY-SA 4.0, via Wikimedia Commons

On November 3, voters in 10 states decided 41 local ballot measures about data centers. In 40 of them, the result went against the buildout. That count comes from Ballotpedia’s tracker of data center ballot measures, and the one exception, Harwood, North Dakota, was a measure that would have added review steps for industrial projects. Voters rejected it 325 to 105.

The headline number is easy to repeat. The more useful number is smaller and more specific: 25 megawatts. Six of the measures that passed set a hard ceiling at 25 MW of demand or peak load, and a seventh is on the ballot in December. That is the line developers, utilities and the equipment makers who sell into data center projects now have to plan around.

The claim

The November vote did not stop the AI buildout. It changed where it can go and how a project has to be sized and financed to get there. The measures that passed are mostly local, mostly in small and midsize towns, and heavily concentrated in Ohio. But they share a design. They do not ban computing. They ban scale, and they set the scale in megawatts, gallons per day, acres, square feet or dollars.

For anyone in the supply chain, that turns a political story into an engineering input. A 25 MW cap is a design spec, and on the evidence below it rules out essentially every campus now being planned for AI training.

The evidence

Ballotpedia counts 50 local data center measures in 13 states during 2026, with 41 on the November 3 ballot. Ohio alone had 21 of the 50, across 18 jurisdictions. Of the 41 November measures, 27 restrictive measures were approved, 13 measures that would have helped projects move forward were defeated, and Harwood was the 41st. By Ballotpedia’s breakdown, the 27 approvals were 5 full bans, 12 partial bans, 3 temporary moratoriums in Maine, 2 zoning measures in Adams County, Ohio, 2 advisory votes in Illinois, 2 voter approval requirements and 1 financial guarantee requirement.

The table below pulls the binding measures that set a number, using the vote counts Ballotpedia reports. The yes share is recomputed from those counts.

Jurisdiction What passed The line Yes No Yes share
Ottawa, KS Ban above the line 25 MW 2,882 1,129 71.9%
Conneaut, OH Ban above the line 25 MW aggregate monthly demand or peak load 2,301 1,218 65.4%
Defiance, OH Ban above the line 25 MW aggregate demand or peak load 3,823 2,083 64.7%
Oregon, OH Ban above the line 25 MW aggregate monthly demand or peak load 4,994 3,235 60.7%
Sunbury, OH Ban above the line 25 MW aggregate monthly demand or peak load 2,809 763 78.6%
Trenton, OH Charter ban on large data centers 25 MW combined demand (per WKRC) 3,541 903 79.7%
Grove City, OH Public vote required 50 contiguous acres, over 20 MW peak, or over 500,000 gallons a day of water 11,317 9,411 54.6%
Janesville, WI Public vote required at the former GM site Project cost over $450 million 16,779 9,932 62.8%
North Berwick, ME Ban above the line 25,000 square feet 2,114 582 78.4%
Perry, OH Financial guarantees for tax incentives Hyperscale developers seeking incentives 946 140 87.1%
Six 25 MW caps combined 20,350 9,331 68.6%

Sources: vote counts from Ballotpedia; Trenton threshold from WKRC Local 12; Perry and Janesville descriptions from Venable. Totals and shares computed by Benderson Media.

Three things stand out. First, the 25 MW caps were not squeakers. Across the six towns, 68.6% of voters backed them, and the weakest, Oregon, still cleared 60%. Second, the most contested measure on the list was the one that did not ban anything. Grove City’s voter approval rule passed with 54.6%, the closest margin in the table. Third, the measures that set dollar and acreage triggers, like Janesville and Grove City, do not stop a project. They add a public vote to the schedule, which for a developer is a different kind of risk: time and uncertainty rather than a flat no.

The defeated measures tell the same story from the other side. In Ashville, Ohio, voters rejected the term summary guiding the village’s negotiations with EdgeConneX on two data centers, 1,469 to 331. In Wilmington, Ohio, four separate referendums to uphold rezonings from rural residential to light industrial, covering about 546 acres in total, each failed with roughly 80% voting no. In Boulder City, Nevada, voters refused to allow data centers in the Eldorado Valley Transfer Area, 5,215 to 2,158.

How big is 25 MW?

The second table puts the line next to real projects named in recent reporting. The multiple is simple division.

Project or unit Size Multiple of a 25 MW cap Source
Prologis data center in Trenton’s industrial park, now in question after the vote 250 MW 10x StockAnalysis
One Venture Global “power island” for on site data center power About 720 MW About 29x StreetSignal
Proposed campus at the former GM site in Janesville 800 MW, $8 billion 32x Venable
OpenAI capacity planned at the PORTS Pike campus in southern Ohio 8 GW 320x Baxtel (citing CNBC)

A town with a 25 MW cap can still host an enterprise server room, a telecom hub or a small edge site. It cannot host anything in this table. The Trenton result shows the cap biting on a real asset: StockAnalysis reports the vote puts in question a 250 MW data center that Prologis is building in the city’s industrial park.

The money was already moving the other way

One week after the vote, SoftBank disclosed about $3.7 billion in losses tied to changes in equipment procurement for US AI data centers, including its Ohio development, according to StreetSignal’s summary of SoftBank’s November 10 earnings materials. Roughly $2.85 billion of that relates to nonrefundable advance payments and $880 million to contract modifications and settlements. SoftBank had committed about $9.5 billion in advance payments, and the same summary says potential discounts on future equipment purchases could reach $2.1 billion. SoftBank has not announced a downsizing of the Ohio project, and StreetSignal notes the procurement decisions predate the election. So this is not a ballot casualty. It is a reminder of how much cash goes out the door for equipment before a site is certain.

Tax incentives are under pressure too. On November 9, an Indianapolis City County Council committee voted 11 to 2 to recommend rejecting about $113 million in tax incentives for a proposed $1.8 billion DC BLOX campus, per StreetSignal citing WFYI. The full council is expected to decide on December 7.

What it means on the ground

For developers, site selection now starts with the ballot map. Ohio had 154 data centers operating, 27 under construction and 57 planned, according to dcmap.us figures cited by Renewable Energy World. The state also carried 21 of this year’s 50 local measures, or 42%. A developer looking at a greenfield site in a small Ohio, Kansas or Maine town now has to ask whether a citizen petition can put the project to a vote before the first transformer is delivered.

For equipment makers and contractors, the risk moves upstream. Big campuses are ordered years ahead. As we covered in our look at the gas turbine shortage and what data centers now pay per kilowatt, power equipment is booked years ahead, and buyers commit cash early to hold a place in line. When a site moves or a scope changes, those deposits become the SoftBank problem: nonrefundable cash, renegotiated contracts and settlement costs. Suppliers holding deposits are protected. Suppliers who built to a schedule without one are not.

For local governments, the tools are now proven. A 25 MW cap, a voter approval trigger and a financial guarantee rule each passed somewhere with a clear majority. Expect them to be copied, because a town clerk can lift the ballot language from the next town over.

Brandon’s Take

From the tooling and manufacturing side, the number in the ordinance is the part that matters. In injection molding, every program starts with a spec: tonnage, shot size, cavitation, cycle time. Change the spec and the whole quote changes. A 25 MW cap is that kind of spec for a data center, and it is low enough that no amount of value engineering turns a 250 MW campus into a compliant one.

What I would watch as a supplier is the terms, not the headlines. The SoftBank numbers show that the expensive part of a site change is the equipment you already paid for. If you sell long lead equipment into this market, the cancellation clause and the deposit schedule are now worth as much attention as the price. And if you are a buyer, assume a meaningful share of sites on your planning list will face a public vote, and do not let a supplier hold your money on a site that has not cleared it.

The other read: the buildout does not vanish, it concentrates. Capacity will flow toward places that have already said yes, toward on site power that does not need a grid fight, and toward larger sites in jurisdictions that are writing rules instead of bans. That favors developers with land and power already in hand and hurts the ones still shopping.

What to watch

  • December 1, Clarksville, Arkansas. Two referendums on bond ordinances, one authorizing up to $50 billion in industrial development bonds for data center equipment leased to Hatchbo LLC and one authorizing up to $5 billion for land leased to SF ARK1, LLC, per Ballotpedia.
  • December 7, Indianapolis. The full council vote on the DC BLOX incentive package.
  • December 15, Mandan, North Dakota. A citizen initiative to prohibit data centers with anticipated capacity or demand of 25 MW or more. If it passes, the 25 MW line spreads to a seventh jurisdiction.
  • Ohio statewide in 2027. A proposed constitutional amendment to ban data centers above 25 MW was certified in March 2026, but the campaign said in June it would miss the July 1 signature deadline and aim for 2027, per Ballotpedia. An October poll by Ohio Northern University and SurveyUSA found 57% of Ohio adults would support it, per StockAnalysis.
  • Federal permitting. The Senate voted 73 to 25 on November 9 to advance debate on a bipartisan permitting bill with provisions aimed at energy infrastructure and data center electricity costs, per StreetSignal. That was a procedural vote, not passage.
  • State executive action. New York already has an executive order establishing a moratorium of up to one year on new hyperscale projects or projects over 50 MW, starting July 14, 2026, according to Renewable Energy World. Watch whether incoming governors elsewhere follow with their own pauses.
  • Supplier commentary. The next round of earnings calls from transformer, switchgear and generator makers is where cancellations or slipped deliveries would show up first.

Sources

This article is analysis and commentary, not investment advice.

Brandon Henderson

Brandon Henderson founded Benderson Media. He has spent more than 15 years in custom injection molding, tooling and global manufacturing, working with factories in China and Vietnam on programs for aerospace and consumer brands. He is a journeyman tool and die maker, CPSP certified, and a Six Sigma Green Belt. Benderson Media covers AI in the real economy: the factories, chips, power and money behind it.

Get The Benderson Brief

Five stories on robots, chips, power and AI money every weekday morning. Free. One click to leave.

Every figure in this piece links to its source. See our editorial standards. Nothing here is investment advice.