Saturday, November 28, 2026 AI in the real economy Get the Brief

Off Balance Sheet Data Center Leases: Big Tech Has $1.3 Trillion Signed but Not Yet Started

Microsoft, Meta, Oracle, Amazon and Alphabet now report $1.3 trillion of data center leases that have not started, 3.4 times the total a year ago. Here is what the footnotes say and who carries the risk.

Off Balance Sheet Data Center Leases: Big Tech Has $1.3 Trillion Signed but Not Yet Started
Image: Gary Halvorson, Oregon State Archives, CC BY 4.0, via Wikimedia Commons

Five companies have signed $1.3 trillion of data center leases that have not started yet. A year ago the same five had $381.8 billion. That is 3.4 times as much in twelve months, and almost none of it sits on a balance sheet today.

The numbers come straight from the latest quarterly filings of Microsoft, Meta, Oracle, Amazon and Alphabet. Each one carries a single sentence, usually in the lease footnote, about leases “not yet commenced.” Alphabet repeated its figure on November 19 in a preliminary prospectus for Canadian dollar notes, telling bond buyers it has $130.5 billion of such leases that are not yet recorded and that a portion of them will become finance lease obligations. That one line is the reason for this piece. Put the five footnotes side by side and you get the largest forward order book in the AI buildout that almost nobody adds up.

The claim

The AI buildout now runs on two budgets. The first is capex, the cash the hyperscalers spend on servers, land and buildings, which grew 1.7 to 3.4 times year over year at these five. The second is the lease book, the buildings other people are putting up for them, and it grew faster overall: 3.4 times in a year across the group. The lease book is where the long dated risk now sits, and it lands on developers, landlords, utilities and equipment makers first.

The evidence

Table 1: Leases signed but not yet started

Company As of A year earlier Latest Added in 12 months Multiple When they start
Microsoft Sep 30, 2026 $106.2B $364.6B $258.4B 3.4x FY2027 to FY2034, terms of 1 to 20 years
Meta Sep 30, 2026 $58.1B $355.7B $297.6B 6.1x Rest of 2026 to 2036, terms up to 30 years
Oracle Aug 31, 2026 $99.8B $288.0B $188.2B 2.9x Q2 FY2027 to FY2029, terms of 15 to 19 years
Amazon Sep 30, 2026 $75.0B $164.9B $89.9B 2.2x $15.0B due through 2027, $114.8B after 2030
Alphabet Sep 30, 2026 $42.6B $130.5B $87.9B 3.1x 2026 to 2031, terms of 1 to 26 years
Total $381.8B $1,303.8B $922.0B 3.4x

Sources: Form 10-Q filings for the quarters shown and the same quarter a year earlier: Microsoft 2026 and 2025; Meta 2026 and 2025; Oracle 2026 and 2025; Amazon 2026 and 2025; Alphabet 2026 and 2025. Figures are future lease payments as each company reports them. Oracle’s fiscal quarter ends August 31; the others end September 30. Multiples and totals computed by Benderson Media.

Meta is the outlier. Its unstarted lease book went from $58.14 billion to $355.73 billion, more than six times. Microsoft added the most in raw dollars after Meta, $258.4 billion. Between them, those two account for $555.9 billion of the $922.0 billion added across the group.

Table 2: The cash budget grew too, but slower

Company Period Year earlier Latest Multiple
Meta Nine months to Sep 30 $48.3B $83.1B 1.7x
Alphabet Nine months to Sep 30 $63.6B $132.0B 2.1x
Amazon Nine months to Sep 30 $92.3B $175.7B 1.9x
Microsoft Quarter to Sep 30 $19.4B $39.4B 2.0x
Oracle Quarter to Aug 31 $8.5B $28.5B 3.4x

Sources: cash flow statements in the same 10-Q filings (purchases of property and equipment; additions to property and equipment for Microsoft; capital expenditures for Oracle). Multiples computed by Benderson Media.

Cash capex rose 1.7 to 2.1 times at four of the five. Oracle more than tripled. The lease books grew faster than capex at four of the five; Oracle is the exception, with capex up 3.4 times and its unstarted lease book up 2.9 times. The direction is clear: a growing share of the AI buildout is being built by someone else and rented back.

What the footnotes changed in a year

The wording moved as much as the numbers. A year ago Meta described its unstarted leases as “mostly for data centers, colocations, and certain network infrastructure,” starting by 2030. Now the list leads with data centers and energy related infrastructure, runs through 2036, and allows lease terms of up to 30 years. Alphabet’s description changed from leases “primarily related to data centers” to “data centers and energy infrastructure.” In other words, two of the five now rent power assets, not just buildings.

Microsoft added a qualifier that was not in last year’s filing: the $364.6 billion comes “with some arrangements subject to certain contractual conditions being met.” Its start window stretched from fiscal 2031 out to fiscal 2034. Oracle’s lease terms lengthened from ten to sixteen years a year ago to fifteen to nineteen years now.

How big against what is already booked

Compare each unstarted figure with the lease liabilities the company already carries:

  • Microsoft: $27.5 billion of operating and $71.0 billion of finance lease liabilities on the books, about $98.5 billion together. The unstarted book is 3.7 times that.
  • Alphabet: $20.5 billion operating plus $3.7 billion finance, about $24.2 billion. The unstarted book is 5.4 times that.
  • Oracle: $34.6 billion operating plus $9.2 billion finance, about $43.8 billion. The unstarted book is 6.6 times that.
  • Meta: $31.2 billion of operating lease liabilities on its balance sheet. The unstarted book is 11.4 times that.

These comparisons are not perfectly like for like. The booked liabilities are discounted to present value and the unstarted figures are mostly future payments. But the gap is too wide for the discount to explain. When these leases start, they move onto the balance sheet as liabilities and begin to show up as rent and depreciation.

The rest of the commitment stack

Leases are not the only promise in the footnotes. Meta reported $454.52 billion of noncancelable contractual commitments, against $81.19 billion a year earlier, a separate figure from its leases. Amazon’s commitments table totals $883.6 billion, up from $376.0 billion, and now includes a $159.6 billion line for property and equipment. Alphabet listed $924.4 billion of material purchase commitments, of which $802.1 billion are multiyear commitments for technical infrastructure, inventory, energy take or pay contracts and content, with $213.4 billion due within twelve months. It also disclosed $10.0 billion of potential future data center and energy infrastructure backstops tied to its investment in the Crux AI joint venture.

The cash side is tight at one of the five. Oracle generated $23.1 billion of operating cash in its fiscal first quarter and spent $28.5 billion on capex. In the same quarter it raised $19.9 billion, net, by selling common stock through an at the market program. Meta, by contrast, generated $96.87 billion of operating cash in nine months against $85.82 billion of capital expenditures including finance lease principal, and guides to $135 billion to $145 billion of capex for 2026.

What it means on the ground

A lease that has not started is a building that someone else is financing and building right now. Every dollar in Table 1 is a developer, a landlord or a neocloud that signed a contract, then went out to buy land, a grid connection, transformers, switchgear, chillers and a construction crew. The hyperscaler’s name on the lease is what lets that developer borrow. The equipment orders follow the lease, not the other way around.

That has three consequences for people who make or buy the hardware.

The order book is longer than capex suggests. Amazon’s own schedule shows only $15.0 billion of its $164.9 billion in unstarted lease payments falls due through 2027. Most of it, $114.8 billion, falls after 2030. Meta’s window runs to 2036. Those are long, slow obligations, and they support long equipment backlogs at the companies that supply the shells. We covered one version of that backlog in our piece on gas turbine queues and the price per kilowatt.

Energy is moving into the lease. When Meta and Alphabet both add energy infrastructure to their lease descriptions in the same year, it tells you the power plant, the substation or the battery yard is increasingly owned by a third party and rented to the data center. That fits the large load tariffs utilities are now writing, which push the cost and risk of new supply onto the customer. A lease is one way to carry that risk without owning the asset.

The risk sits with the builder until the keys change hands. Microsoft’s new qualifier matters here. If some arrangements depend on conditions being met, then some of that $364.6 billion can slip or shrink if a site misses its power date or its construction schedule. The developer who already bought the long lead equipment carries that gap.

Brandon’s Take

From the tooling side, this reads like a program award, not a purchase order. When a big customer awards a program, the supplier builds molds, buys steel and books press time months before the first part ships, and the customer’s paperwork is what the supplier’s lender looks at. A lease not yet commenced works the same way. The hyperscaler has committed. The builder has spent. The money changes hands later.

The lesson from manufacturing is that the award is real but the volume is not guaranteed. Programs get pushed, rescoped or cut, and the supplier who tooled up for the forecast eats the gap. I would watch the developers and equipment makers in the middle of this, not the five names at the top. Their balance sheets are where a delayed site shows up first.

The other thing I would watch is lead time. Oracle says its leases start between the second quarter of fiscal 2027 and fiscal 2029. That is a short runway for buildings this size. Electrical gear has to be ordered well before the shell is finished, so if those buildings are going to open on time, the transformers and switchgear for them should already be on order.

What to watch

  • Oracle’s fiscal second quarter 10-Q, due after its quarter ended November 30. The lease commitment line and the gap between operating cash and capex are the two numbers to check.
  • Year end 10-K filings from Meta, Amazon and Alphabet early next year. If the unstarted lease books keep growing at this pace, the five could pass $1.5 trillion. If they flatten, the buildout is shifting from signing to building.
  • Conditional language. Whether other companies follow Microsoft in saying some leases depend on conditions being met. More hedged wording would signal more sites at risk of slipping.
  • Commencements. As leases start, booked lease liabilities and depreciation should rise. Alphabet’s nine month depreciation already went from $15.1 billion to $22.0 billion, and Microsoft’s quarterly depreciation from $7.1 billion to $11.1 billion.
  • Bond market disclosure. Alphabet put the $130.5 billion figure in front of bond buyers this month. Watch whether credit investors start pricing unstarted leases like debt.

None of this is investment advice. It is a read of what five companies have told the SEC they have already signed.

Sources

Get The Benderson Brief in your inbox every weekday morning. Follow @bendersonmedia on X for the daily charts.

Brandon Henderson

Brandon Henderson founded Benderson Media. He has spent more than 15 years in custom injection molding, tooling and global manufacturing, working with factories in China and Vietnam on programs for aerospace and consumer brands. He is a journeyman tool and die maker, CPSP certified, and a Six Sigma Green Belt. Benderson Media covers AI in the real economy: the factories, chips, power and money behind it.

Get The Benderson Brief

Five stories on robots, chips, power and AI money every weekday morning. Free. One click to leave.

Every figure in this piece links to its source. See our editorial standards. Nothing here is investment advice.

Keep reading